ENROLLED ORIGINAL
A RESOLUTION
23-444
IN THE COUNCIL OF THE DISTRICT OF COLUMBIA
July 7, 2020
To declare the existence of an emergency with respect to the need to approve Change Order Nos.
04, 05, 06, and 07 to Contract No. DCAM-18-CS-0117 between the Department of
General Services and Stevens School Developer, LLC for design-build services for
Thaddeus Stevens School Exterior Renovation, and to authorize payment in the aggregate
amount of $1,025,455 for the goods and services received and to be received under these
change orders.
RESOLVED, BY THE COUNCIL OF THE DISTRICT OF COLUMBIA, That this
resolution may be cited as the Change Order Nos. 04, 05, 06 and 07 to Contract No. DCAM-18-
CS-0117 Approval and Payment Authorization Emergency Declaration Resolution of 2020.
Sec. 2 (a) There exists an immediate need to approve Modification Nos. 04, 05, 06, and
07 to Contract No. DCAM-18-CS-0117 with Stevens School Developer, LLC for design-build
services for Thaddeus Stevens School exterior renovation (Contract) and to authorize payment
in the aggregate amount of $1,025,455 for design-build services received and to be received
under the change orders.
(b) On July 6, 2019, the Contract was deemed approved by the Council as CA23-0211.
The underlying Contract, as submitted to Council, included an initial not-to-exceed (NTE)
amount of $3,047,568.
(c) The Department of General Services subsequently issued Modification No. 01, in the
amount of $0, which was executed on August 8, 2019, and which added administrative language
to the Contract. Modification No. 02 was executed on August 18, 2019 and increased the NTE
amount by $996,230. Modification No. 03 was previously submitted and approved by the
Council by Change Order Nos. 1 through 3 to Contract No. DCAM-18-CS-0117 Approval and
Payment Authorization Emergency Act of 2019, effective, November 26, 2019 (D.C. Act 23-
169; 66 DCR 15901) and increased the NTE amount by $6,455,776.00 to establish a final lump
sum Contract price. Modification No. 04 was executed on January 29, 2020, and increased the
lump sum Contract price by $425,868. Modification No. 05 was executed on March 30, 2020,
and increased the lump sum Contract price by $137,997. Modification No. 06 was executed on
June 4, 2020, and increased the lump sum Contract price by $273,215.
1
ENROLLED ORIGINAL
(d) Council approval is now required as proposed Modification No. 07 would increase the
Contract value by $188,375. The aggregate increase to the total Contract value, via Modification
Nos. 04, 05, 06 and 07, would be $1,025,455.
(e) Proposed Modification No. 07 would cause the aggregate value of all modifications
issued after the last Council approval to exceed $1 million; thus, Council approval of
Modification Nos. 04, 05, 06, and 07 is now required pursuant to section 451 of the District of
Columbia Home Rule Act, approved December 24, 1973 (87 Stat. 803; D.C. Official Code 1-
204.51).
Sec. 3. The Council of the District of Columbia determines that the circumstances
enumerated in section 2 constitute emergency circumstances making it necessary that the
Modification Nos. 04, 05, 06 and 07 to Contract No. DCAM-18-CS-0117 with Stevens School
Developer, LLC Approval and Payment Authorization Emergency Act of 2020 be adopted after
a single reading.
Sec. 4. This resolution shall take effect immediately.
2