ENROLLED ORIGINAL
A RESOLUTION
23-441
IN THE COUNCIL OF THE DISTRICT OF COLUMBIA
July 7, 2020
To declare the existence of an emergency with respect to the need to approve Modification Nos.
8, 10, and 12 to Contract No. DCAM-17-CS-0041A between the Department of General
Services and Smoot Construction Company of Washington, DC, increasing the aggregate
amount of the Contract to $29,710,565.61, and to authorize payment to Smoot
Construction Company of Washington, DC for construction management at risk services
received and to be received under these modifications.
RESOLVED, BY THE COUNCIL OF THE DISTRICT OF COLUMBIA, That this
resolution may be cited as Modification Nos. 8, 10 and 12 to Contract No. DCAM-17-CS-
0041A with Smoot Construction Company of Washington, DC Approval and Payment
Authorization Emergency Declaration Resolution of 2020.
Sec. 2. (a) There exists an immediate need to approve Modification Nos. 8, 10, and 12 to
Contract DCAM-17-CS-0041A (Contract) between the Department of General Services and
Smoot Construction Company of Washington, DC (Contractor), which would increase the
amount of the Contract to $29,710,565.61 and authorize payment to the Contractor for
construction management at risk services received and to be received under these Contract
modifications.
(b) Modification No. 8 in the amount of $345,086.72 and Modification No. 10 in the
amount of $608,944.29 increased the Contracts aggregate value by $954,031.01, an amount
under $1 million; thus, Council approval was not required. Proposed Modification No. 12 in the
amount of $254,112 would increase the Contracts aggregate value by $1,208,143.61, from
$28,502,422 to $29,710,565.61.
(c) The aggregate increase of Modification Nos. 8, 10, and 12 is in excess of $1 million
during a 12-month period; therefore, Council approval is required pursuant to section 451 of the
District of Columbia Home Rule Act, approved December 24, 1973 (87 Stat. 803; D.C. Official
Code 1-204.51), and the requirements of section 202 of the Procurement Practices Reform Act
of 2010, effective April 8, 2011 (D.C. Law 18-371; D.C. Official Code 2-352.02).
(d) Council approval of Modification Nos. 8, 10, and 12 is necessary to allow the
continuation of essential construction management at risk services at the Ward 3 Short Term
1
ENROLLED ORIGINAL
Family Housing facility and to compensate the Contractor for services provided and to be
provided under these Contract modifications.
Sec. 3. The Council of the District of Columbia determines that the circumstances
enumerated in section 2 constitute emergency circumstances making it necessary that the
Modification Nos. 8, 10 and 12 to Contract No. DCAM-17-CS-0041A with Smoot Construction
Company of Washington, DC Approval and Payment Authorization Emergency Act of 2020 be
adopted after a single reading.
Sec. 4. This resolution shall take effect immediately.
2