The bill amends RCW 43.52.560 to update the purchasing thresholds for joint operating agencies regarding contracts for materials, equipment, supplies, and construction work. Specifically, the estimated cost threshold for purchasing items is increased from $15,000 to $30,000, while the threshold for construction work is raised from $25,000 to $150,000 when more than one craft or trade is involved. Additionally, if only a single craft or trade is involved, the threshold is set at $75,500.
These changes aim to modernize the procurement process for joint operating agencies, ensuring that the thresholds reflect current economic conditions and allowing for more efficient contract management. The bill maintains the requirement for sealed bids for contracts, as stipulated in RCW 54.04.070 and 54.04.080.
Statutes affected: Original Bill: 43.52.560
Engrossed Bill: 43.52.560
Bill as Passed Legislature: 43.52.560
Session Law: 43.52.560