This bill amends the Pennsylvania Municipalities Planning Code to introduce new definitions and requirements related to data centers, specifically hyperscale data centers. It adds definitions for "data center" and "hyperscale data center," specifying the characteristics and energy requirements of these facilities. A "data center" is defined as a facility primarily used for housing servers and data storage systems, equipped with backup power and cooling infrastructure. A "hyperscale data center" is further defined based on its energy load, requiring a peak load of at least 25 megawatts for a single facility or 50 megawatts for multiple facilities.

Additionally, the bill mandates that zoning hearing boards must hold at least two public meetings to solicit comments before approving applications for hyperscale data centers. These meetings are required to be advertised through public notice, ensuring community input in the decision-making process. The act will take effect 60 days after its passage.

Statutes/Laws affected:
Printer's No. 1955 (Sep 24, 2026): P.L.805, No.247