Legislative Analysis
Phone: (517) 373-8080
STATE CONTRACTING SELECTION PROCESS
http://www.house.mi.gov/hfa
House Bill 5654 (H-1) as reported from committee Analysis available at
Sponsor: Rep. Amos O’Neal http://www.legislature.mi.gov
Committee: Regulatory Reform
Complete to 6-20-24
SUMMARY:
House Bill 5654 would amend the Management and Budget Act to modify the requirements
for the section of architects for architectural services, professional engineers for engineering
services, professional surveyors for land surveying services, and qualified firms for proposed
projects of the Department of Technology, Management, and Budget (DTMB) and state
agencies for the period between January 1, 2025, and December 31, 2032.
Currently, the act requires selections for these services to be made in accordance with
competitive, qualifications-based selection processes and procedures for the type of
professional service, as determined by DTMB.
Selecting a qualified firm
Under the bill, from January 1, 2025, to December 31, 2032, in selecting professionals for these
services with an estimated cost of $250,000 or more, DTMB or the relevant state agency would
have to publish a notice requesting a statement of interest in the proposed project by any
qualified firm, along with a statement of qualifications and performance data from that
qualified firm. The published notice would state the general scope and nature of the proposed
project for which services are required and include contact information for a representative of
the department or state agency who can provide further details of the proposed project.
Qualified firm would mean a sole proprietorship, partnership, corporation, or limited
liability company through which a person licensed as an architect, professional
engineer, or professional surveyor under the Occupational Code offers or provides
architectural services, engineering services, or land surveying services to the public.
The department or state agency would have to evaluate the statements of interest, statements
of qualifications, and performance data submitted by qualified firms. In evaluating a firm for
a proposed project, they would have to consider all of the following:
• Qualifications of the firm.
• Ability of the professional personnel of the firm.
• Past record and experience of the firm.
• Any other qualifications-based factors that the department or state agency determines
are applicable.
The department or agency could also conduct discussions with and require presentations by
any qualified firm being considered to provide the required services.
House Fiscal Agency Page 1 of 5
Negotiating an agreement
Based on the information gathered as required or allowed by the bill, DTMB or the state agency
would have to select and rank the qualified firms in order based on their qualifications and
enter into contract negotiations with the highest-ranked firm. If the department or agency is
unable to negotiate a contract with the firm, the negotiation would be formally terminated and
would begin with the next highest-ranked firm. This would continue until an agreement is
reached or the process is terminated.
If a no satisfactory contract can be reached with any of the selected firms, the department or
state agency would have to reevaluate the services requested, including the estimated value,
scope, complexity, and fee requirements.
Waiving requirements
The bill would allow DTMB or a state agency to waive the requirements described above if it
determines that an emergency situation exists and a qualified firm must be selected in an
expeditious manner. The requirements could also be waived if the proposed project is for
energy conservation improvements to state facilities described in section 253 of the act. 1
Report
The bill would require DTMB to submit a report to the legislature annually on January 1 from
2026 to 2033 that includes all of the following information for the immediately preceding year:
• A summary of whether qualified firms that were selected for contracts under the bill
offered new ideas, technology, materials, construction techniques, or other innovations.
• A summary of whether projects contracted for under the bill were completed on
schedule or otherwise met scheduled deadlines.
• A summary of whether projects contracted for under the bill stayed on budget.
• An analysis of whether there was greater collaboration between the department or state
agency, as applicable, and the qualified firm to reduce misunderstandings and project
risk compared to projects contracted prior to the bill’s implementation.
• An indication of whether design documents of projects contracted for under the bill are
considered to be at a high level.
Exemption
The bill’s requirements would not apply to selections of contractors if the selections are in
compliance with 23 USC 112, 2 which regulates bidding requirements for state transportation
departments.
MCL 18.1237b
BRIEF DISCUSSION:
The bill is similar to Senate Bill 642 of 2021, 3 which was pocket vetoed by Governor
Whitmer. 4
1
https://www.legislature.mi.gov/Laws/MCL?objectName=MCL-18-1253
2
https://www.law.cornell.edu/uscode/text/23/112
3
https://www.legislature.mi.gov/Bills/Bill?ObjectName=2021-SB-0642&QueryID=160300287
4
If the governor does not sign a bill within 14 days after getting it and the legislature has adjourned to end the session,
the bill does not take effect and is said to have been “pocket vetoed.” Senate Bill 642 was pocket vetoed on January
House Fiscal Agency HB 5654 (H-1) as reported Page 2 of 5
Supporters of the bill argue that it would help to ensure transparency and equal opportunity in
the selection process.
In testimony on Senate Bill 642 last session, DTMB testified that Michigan uses a “best value”
system rather than a straight “low-bid” system when determining which vendor to select for a
service. The evaluation process is weighted, with 80% based on performance quality and other
qualification and 20% based on estimated hours and cost to complete the work. The department
opposed the proposal, arguing that estimated hours should be a part of the information required
during the vendor selection process, while design firms opposed adding the requirement,
preferring instead to have it be determined during the contract negotiation process.
FISCAL IMPACT:
House Bill 5654 could result in increased costs to the state in the short-term and cost savings
to the state in the long-term, for an overall indeterminate fiscal impact. The state could see
increases in state contracting costs for architectural, engineering, and surveying services for
state design and construction projects if qualified, lower-priced firms are passed over in favor
of more qualified and higher-priced firms. The bill would largely codify much of the current
procurement process used by DTMB when evaluating and selecting contracted services, but
costs would not be included among the required factors for evaluating firms in the competitive
bid process for proposed state projects as they are under current procurement practices.
DTMB reports that a majority of design contracts go to those firms that provided the lowest
cost proposal. Additionally, DTMB reports that a review of state architecture and engineering
service projects over $250,000 since 2014 showed an error and omissions rate of 0.15% of the
related construction costs, well below the 3% to 5% rate industry standard that would lead to
corrective action. Considering this, DTMB does not believe there would be significant cost
savings through error reduction and believes that the bill would likely lead to increased costs
to the state in the short and long terms.
Qualifications-based selection has been shown in studies to offset savings from low-bid or best
value procurement processes and also significantly reduce long-term costs in the construction
of projects and the maintenance of facilities through various life-cycle costs.
Any potential short-term cost increase would affect any state department or agency that
contracts for projects utilizing these services. In FY 2021-22, the state Design and Construction
office under DTMB oversaw approximately 550 active projects with a total project value of
approximately $1.2 billion.
Additionally, DTMB may incur additional costs related to the bill’s annual reporting
requirement if existing staff is not able to adequately organize and report the required
information.
The bill would have no fiscal impact on local units of government.
11, 2023, when still unsigned having been presented to the governor on December 28, 2022, which was also the date
the legislature adjourned sine die (without day) to end the legislative session.
House Fiscal Agency HB 5654 (H-1) as reported Page 3 of 5
POSITIONS:
A representative of the American Council of Engineering Companies of Michigan and the
Michigan Section of the American Society of Civil Engineers testified in support of the bill.
(6-11-24)
The following entities indicated support for the bill:
• American Society of Architects (6-11-24)
• Cincar Consulting Group (6-11-24)
• Gowrightman (6-11-24)
• Great Lakes Chapter of the International Institute of Building Enclosure Consultants
(6-11-24)
• HED Design (6-11-24)
• HNTB Corporation (6-11-24)
• Hubbell, Roth, & Clark (6-11-24)
• Johnson Controls (6-18-24)
• Michigan Society of Professional Engineers (6-11-24)
• Michigan Society of Professional Surveyors (6-11-24)
• OHM Advisors (6-11-24)
• Sedgewick & Ferweda Architects (6-11-24)
• SME USA (6-11-24)
• Somat Engineering Inc. (6-11-24)
• Wade Trim (6-11-24)
• WSP Michigan (6-11-24)
• WSP USA (6-11-24)
The Department of Technology, Management, and Budget indicated opposition to the bill.
(6-18-24)
Legislative Analyst: Alex Stegbauer
House Fiscal Agency HB 5654 (H-1) as reported Page 4 of 5
Fiscal Analyst: Michael Cnossen
■ This analysis was prepared by nonpartisan House Fiscal Agency staff for use by House members in their
deliberations and does not constitute an official statement of legislative intent.
House Fiscal Agency HB 5654 (H-1) as reported Page 5 of 5

Statutes affected:
Substitute (H-1): 18.1237
House Introduced Bill: 18.1237
As Passed by the House: 18.1237