The bill amends K.S.A. 66-1,178 concerning the siting permits for electric transmission lines by extending the time frame for the state corporation commission to issue a final order on such applications from 120 days to 180 days. Additionally, it introduces new legislative intent that encourages the commission to process applications expeditiously and, when possible, to issue final orders in less than the established 180-day period. The bill also includes provisions for public hearings and evidentiary hearings related to the applications.

Furthermore, the bill repeals the existing section of K.S.A. 66-1,178, effectively replacing it with the updated language that reflects the new time frame and intent for expedited processing. This legislative change aims to streamline the permitting process for electric transmission lines while ensuring that necessary public hearings are conducted to assess the proposed locations.