The bill amends K.S.A. 66-1,178, which governs the process for electric transmission line siting permits by extending the time frame for the state corporation commission to issue a final order on such applications from 120 days to 180 days. Additionally, it introduces new legislative intent that encourages the commission to expedite the review process and, when possible, issue final orders in less than the established 180-day period.

Furthermore, the bill repeals the existing section of K.S.A. 66-1,178, effectively replacing it with the updated provisions. The changes aim to streamline the permitting process while ensuring that the commission maintains its customary practices in handling applications for electric transmission line siting permits. The act will take effect upon publication in the statute book.

Statutes affected:
As introduced: 66-1
As Amended by House Committee: 66-1