Clarifies that the statute of repose applies to contract, tort, and statutory claims. Clarifies the required contents of a notice of claim of a construction defect served on a contractor. Clarifies the process and time frame by which a claimant may accept or reject a contractor's offer to settle and authorize repairs. Clarifies the mediation process for construction defect claims. Clarifies the statute of limitation or repose for construction defect claims. (CD1)
Statutes affected: HB420: 657-8, 672E-3, 672E-4, 672E-6
HB420 HD2: 657-8, 672E-3, 672E-4, 672E-6
HB420 HD3: 657-8, 672E-3, 672E-4, 672E-6
HB420 HD1: 657-8, 672E-3, 672E-4, 672E-6
HB420 SD1: 657-8, 672E-3, 672E-4
HB420 CD1: 657-8, 672E-3, 672E-4, 672E-6, 672E-7, 672E-8
HB420 SD2: 657-8, 672E-3, 672E-4, 672E-6, 672E-7, 672E-8
Latest: 657-8, 672E-3, 672E-4, 672E-6