The proposed Modification No. 1 to Contract DCAM-24-CS-RFP-0003 with GCS, Inc., dba GCS-SIGAL, aims to establish a Guaranteed Maximum Price (GMP) of $21,112,874 for the Construction Management At-Risk Services for the Southeast Tennis & Learning Center South Campus. This modification will increase the contract's Not-to-Exceed (NTE) amount from $3,990,000 to $15,990,000, allowing the contractor to proceed with construction services while the Department of Parks and Recreation secures funding for the remaining GMP. The contractor is restricted from expending more than $15,990,000 until further written authorization is provided by a Contracting Officer and approved by the Council. The substantial completion date for the project is set for April 9, 2026.

The bill also outlines the approval process for a capital reprogramming request related to the project, emphasizing the need for Council approval due to the modification amount exceeding $1 million. It establishes a shared savings model for cost savings from the Construction Contingency, dividing any savings between the Department and the CMAR on a 70/30 basis. The agreement mandates that the CMAR perform all necessary work while adhering to stringent contract requirements and allows for a "fast-track" construction method. The bill ensures that all prior agreements remain unaffected unless modified in this amendment and establishes that the agreement constitutes the entire understanding between the parties, superseding any previous arrangements.