The proposed Modification No. 4 to Contract No. DCAM-22-CS-RFP-0009 with Chiaramonte Construction Company seeks to increase the contract's not-to-exceed amount by $17,859,313.29, raising the total contract value from $8,240,281 to $26,099,594.29. This modification is essential for completing the modernization of Stoddert Elementary School, which includes extensive work such as demolition, structural improvements, and the installation of various systems. The substantial completion dates for the project are set for July 15, 2025, for the east end, July 15, 2026, for the west end, and August 8, 2026, for the cafeteria remodel. The modification also includes a release clause where the contractor waives any claims against the Department related to delays or additional costs arising from this modification.

Additionally, the bill outlines the responsibilities and agreements between the Design-Builder and the Department regarding the construction of the East End and West End Additions, establishing a Guaranteed Maximum Price (GMP) of $26,099,594.29. The contractor is responsible for any costs exceeding this maximum price, and the bill emphasizes compliance with the Contract Documents, ensuring that all work inferred must be completed without increasing the GMP or extending the contract time unless specified. The bill also introduces new requirements for contractor design responsibility and construction waste management, enhancing accountability and environmental stewardship in the project. Overall, the legislation aims to facilitate a successful construction process for the classroom addition at Stoddert Elementary School while adhering to regulatory requirements and budgetary constraints.