MURIEL BOWSER MAYOR June 30, 2023 The Honorable Phil Mendelson Chairman Council of the District of Columbia John A. Wilson Building 1350 Pennsylvania Avenue NW, Suite 504 Washington, DC 20004 Dear Chairman Mendelson: Pursuant to section 451 of the District of Columbia Home Rule Act (D.C. Official Code § 1-204.51) and section 202 of the Procurement Practices Reform Act of 2010 (D.C. Official Code § 2-352.02), enclosed for consideration and approval by the Council of the District of Columbia is proposed Modification No. 1 to Contract No. DCAM-21-CS-IFB-0003 with Fort Myer Construction Corporation, increasing the not-to-exceed amount by $6,804,102.87, from $22,992,912.30 to $29,797,015.17, and extending the period of performance through December 19, 2023. Under proposed Modification No. 1, Fort Myer Construction Corporation will continue to provide construction services required to complete the infrastructure improvements for 13th Street, SE, a major part of the redevelopment of the St. Elizabeths East Campus and the required improvements to support the construction of the new hospital under its contract with the Department of General Services (“DGS”). If you have any questions regarding the proposed contract modification, please contact Delano Hunter, Acting Director of DGS, or have your staff contact George G. Lewis, DGS’s Chief of Contracts and Procurement, at (202) 727-2800. I look forward to the Council’s favorable consideration of this contract modification. Sincerely, Muriel Bowser GOVERNMENT OF THE DISTRICT OF COLUMBIA DEPARTMENT OF GENERAL SERVICES Pursuant to section 202(c) of the Procurement Practices Reform Act of 2010, as amended, D.C. Official Code § 2-352.02(c), the following contract summary is provided: COUNCIL CONTRACT SUMMARY (Standard) Modification No. 1 to Contract No. DCAM-21-CS-IFB-0003 Redevelopment St. Elizabeths East Campus – 13th Street SE Infrastructure Improvements (A) Contract Number: DCAM-21-CS-IFB-0003 (the “Contract”) Contractor: Fort Myer Construction Corporation (the “Contractor”) Proposed Increased Amount Via Modification No. 1: $6,804,102.87 Total Contract Not-to-Exceed (“NTE") Amount: $29,797,015.17 Unit and Method of Compensation: Progress payments based on Fixed Unit Prices Term of Contract: January 5, 2022 – December 19, 2023 Type of Contract: Fixed Unit Prices with NTE amount Source Selection Method: Competitive Sealed Bid (Invitation for Bid) (B) For a contract containing option periods, the contract amount for the base period and for each option period. If the contract amount for one or more of the option periods differs from the amount for the base period, provide an explanation of the reason for the difference: N/A 1 (C) The goods or services to be provided, the methods of delivering goods or services, and any significant program changes reflected in the proposed modification: The Contract between the Department of General Services (“DGS” or the “Department”) and the Fort Myer Construction Corporation (the “Contractor”) requires the Contractor to provide construction services to complete the infrastructure improvements to 13th Street SE, a major effort in the redevelopment of the St. Elizabeths East Campus. The work includes, but is not limited to, providing site and utility demolition, erosion and sediment control measures, new underground wet and dry utilities, and a new roadway of approximately 1,740 LF for 13th Street SE, including the intersections at Cypress Street SE, Cherry Street SE, and the new entrance roadway and security booth. The scope of work also includes construction of several all-weather DC Water and WMATA maintenance roadways and storm sewer and sanitary sewer infrastructure improvements in the ravine area. The underlying Contract was deemed approved by the Council on December 24, 2021, as CA24- 0343 with a Not-to-Exceed (“NTE”) amount of $22,992,912.30. The Department now seeks Council approval to execute proposed Modification No. 1. If approved, Modification No. 1 will increase the Contract’s NTE from $22,992,912.30 by $6,804,102.87 to $29,797,015.17. Modification No. 1 will increase the NTE amount to fund additional services resulting from unforeseen site conditions, removal and disposal of contaminated soil, fulfillment of DC Water and WMATA requirements, and additional needs resulting from the redesign of the storm drainage system. Modification No. 1 will also extend the final completion date to December 19, 2023. As the proposed modification would increase the Contract value by more than $1 million, Council approval is required for this contract action. (D) The selection process, including the number of offerors, the evaluation criteria, and the evaluation results, including price, technical or quality, and past performance components: The underlying Contract was competitively bid and previously submitted to and approved by the Council (CA24-0343) on December 24, 2021. (E) A description of any bid protest related to the award of the Contract, including whether the protest was resolved through litigation, withdrawal of the protest by the protestor, or voluntary corrective action by the District. Include the identity of the protestor, the grounds alleged in the protest, and any deficiencies identified by the District as a result of the protest: The award of the Contract was not protested. (F) The background and qualifications of the proposed contractor, including its organization, financial stability, personnel, and performance on past or current government or private sector contracts with requirements similar to those of the proposed contract modification: 2 For nearly 50 years, Fort Myer Construction Corporation (the “Contractor”) has served the infrastructure needs of the District of Columbia (the “District”), Maryland, and Virginia. The Contractor has received a number of awards for its infrastructure work throughout the District, Maryland and Virginia and has completed notable projects such as the widening of Route 1 in Prince William County, Virginia, the reconstruction of the intersection of MD 97 at Randolph Road in Montgomery County, Maryland, construction of the District’s fiber optic network, and the 31st Street Bridge in the District. The Contractor reports over 900 employees and a fleet of over 1,100 modern vehicles. The Contractor has performed satisfactorily on this and other projects on the St. Elizabeths East Campus. The Contractor has been determined responsible in accordance with 27 DCMR 4706.1. (G) A summary of the subcontracting plan required under section 2346 of the Small, Local, and Disadvantaged Business Enterprise Development and Assistance Act of 2005, as amended, D.C. Official Code § 2-218.01 et seq. (“Act”), including a certification that the subcontracting plan meets the minimum requirements of the Act and the dollar volume of the portion of the Contract to be subcontracted, expressed both in total dollars and as a percentage of the total Contract amount: The Contractor is a certified business enterprise in accordance with the Act (CBE Number: LZXM44731122023). The Contractor submitted a subcontracting plan that meets the minimum requirements of the Act. Contract Dollar Value $29,797,015.17 Contractor Self-Performing $20,668,108.17 Subcontracting Effort $9,128,907.00 Subcontracting Plan Dollar Value $9,128,907.00 Subcontracting % 100% (H) Performance standards and the expected outcome of the proposed contract modification: The Contractor is required to provide all of the labor, tools, equipment, and materials and other services necessary for completion of the Project. The proposed Modification No. 1 extends the Project completion date to December 19, 2023. The Contractor is subject to liquidated damages of $5,000 per workday of delay for failure to timely complete the work for the Project. Additionally, the Department may also withhold payments to the Contractor based on defects in any application for payment or performance on the Project. In general, the Contractor must perform the requirements contained in the Contract and meet or exceed the performance standards therein. The Contractor’s performance will be monitored by DGS staff and DGS’ designated Program Manager. (I) The amount and date of any expenditure of funds by the District pursuant to the Contract prior to its submission to the Council for approval: N/A 3 (J) A certification that the proposed contract modification is within the appropriated budget authority for the agency for the fiscal year and is consistent with the financial plan and budget adopted in accordance with D.C. Official Code §§ 47-392.01 and 47-392.02: The Office of the Chief Financial Officer has certified that the proposed Modification No. 1’s NTE amount is consistent with the Department’s budget and that adequate funds are available in the Department’s budget in accordance with §§47-392.01 and 47-392.02. The applicable Fiscal Sufficiency certification accompanies this Council Package. (K) A certification that the proposed modification is legally sufficient, including whether the proposed contractor has any pending legal claims against the District: Proposed Modification No. 1 has been deemed legally sufficient by the Department’s Office of the General Counsel and the Contractor does not appear to have any currently pending legal claims against the District. (L) A certification that the Citywide Clean Hands database indicates that the proposed contractor is current with its District taxes. If the Citywide Clean Hands Database indicates that the proposed contractor is not current with its District taxes, either: (1) a certification that the contractor has worked out and is current with a payment schedule approved by the District; or (2) a certification that the contractor will be current with its District taxes after the District recovers any outstanding debt as provided under D.C. Official Code § 2- 353.01(b): The Citywide Clean Hands database indicates that the Contractor is in compliance with the Government of the District of Columbia tax laws and regulations. The applicable Clean Hands certification for the Contractor accompanies this Council Package. (M) A certification from the proposed contractor that it is current with its federal taxes, or has worked out and is current with a payment schedule approved by the federal government: The Contractor has certified that it is current with its federal taxes. (N) The status of the proposed contractor as a certified local, small, or disadvantaged business enterprise as defined in the Small, Local, and Disadvantaged Business Enterprise Development and Assistance Act of 2005, as amended; D.C. Official Code § 2-218.01 et seq.: According to the DSLBD’s website, the Contractor is a certified Local, and Long Time Resident Owned Business Enterprise and a Local Manufacturing Business Enterprise located in Development Enterprise Zone. The Contractor’s CBE Number is LZXM44731122023, with an expiration date of December 21, 2023. (O) Other aspects of the proposed contract that the Chief Procurement Officer considers significant: None 4 (P) A statement indicating whether the proposed contractor is currently debarred from providing services or goods to the District or federal government, the dates of the debarment, and the reasons for debarment: The Contractor is not debarred from providing services to the Government of the District of Columbia or the Federal Government according to the Office of Contracts & Procurement’s Excluded Parties List and the Federal Government’s Excluded Parties List. (Q) Any determination and findings issues relating to the Contract’s formation, including any determination and findings made under D.C. Official Code § 2-352.05 (privatization contracts): None (R) Where the Contract, and any amendments or modifications, if executed, will be made available online: Contract award information is available on the Department’s website. Copies of contract documents will be made available upon request. (S) Where the original solicitation, and any amendments or modifications, will be made available online: The original solicitation and any amendments can be found on the Department’s web site, at https://dgs.dc.gov/event/dcam-21-cs-ifb-0003-redevelopment-st-elizabeths-east-campus-13th- street-se-infrastructure (T) A notation identifying: (i) whether the Contractor is a covered contractor, as that term is defined in D.C. Official Code § 1-1161.01; and (ii) to which prohibited recipients, as that term is defined in D.C. Official Code § 1-1161.01(45D), the Contractor is prohibited from making campaign contributions and during what prohibited period, as that term is defined in § 1-1161.01(45C). Based upon a certification from the Contractor, the Contractor has not been determined to be in violation of D.C. Official Code § 1-1163.34a. 5 ()8784ÿÿ458ÿ 474ÿÿ* +8ÿÿ458ÿ58ÿ! *ÿ+87 0010ÿ345ÿ6478849ÿ6 +8ÿÿ,-ÿ.ÿ/8)88ÿ 549ÿÿ113  48ÿÿ48 8ÿ039ÿ1 48ÿ 8711100 !+/,ÿ01"/ÿ+6,/2,#+ÿ+/3+/4,#+ !"#ÿ$$%$$$&& 5ÿ/ÿ6,ÿ"  8ÿ#ÿ0&33&& 466#(,+ÿÿÿ110%0&1& ÿ ÿ @ABCDED@FCAÿHEÿ@IAFJÿKFJLM 4 ÿ78;748.ÿÿ458ÿ*8ÿ6 .ÿ9489ÿ458ÿ )8ÿ788788.ÿ.).*N8449ÿ5 ÿÿ44. * *49ÿO45ÿ458ÿ 474ÿÿ* ÿ+8ÿÿ,-ÿ.ÿ/8)88ÿ7ÿ458ÿ8;7484ÿÿ";*984 687)8<ÿ4 ÿÿ458ÿ.48ÿ )89ÿ458ÿ.).*N8449ÿ5 ÿ;*8.ÿO45ÿÿ.8ÿPÿ35%9ÿÿ4587878 45 ÿ87448ÿÿ*8ÿ6 .ÿÿ 8.< ,#,"ÿ35<ÿ,4Q4,#+9ÿ#"6#(9ÿ3"/0#,69ÿ466"660",69ÿ4ÿ!""6 643,"/ÿÿ(""/4ÿ#"6" 627643,"/ÿ##<ÿ"4ÿ646ÿ7"!+/"ÿ/""#>#(ÿ4ÿ#"6"ÿ+/ÿ3"/0#, <<ÿ+"ÿPÿ35%ÿR11S Pÿ35%ÿ3/+6#7#,#+ÿ4(4#6,ÿ#6624"ÿ+!ÿ#"6"ÿ+/ÿ3"/0#, 445788.ÿ79ÿ08*.ÿ8: 775ÿ589ÿ**84ÿ.ÿ"7884ÿ4. 474 ,ÿ)*.48ÿ45 ÿ874489ÿ;*8 8ÿ) 4ÿ09,-<<)<ÿ+ÿ458ÿ09,-ÿÿ58;89ÿ*:ÿ458 => *.48ÿÿ87448ÿÿ*8ÿ6 .?ÿ59;87*:ÿ.87ÿ458ÿ*8ÿ6 .ÿ84< TTUTÿVWXÿMWYZZWÿM[\ÿM]^WZÿ[_`U\ÿ[abX^cdWec\ÿL@ÿ_UU_VfgXecZhÿi_U_jÿ̀_VklUVlfmnCaopL@pdeq ÿ GOVERNMENT OF THE DISTRICT OF COLUMBIA DEPARTMENT OF GENERAL SERVICES Office of the Chief Financial Officer Memorandum To: Delano Hunter Acting Director From: Antoinette Hudson Beckham Agency Fiscal Officer Reference: Redevelopment of St. Elizabeths East Campus – 13th Street SE Infrastructure Improvements Date: June 14, 2023 Subject: Fiscal Sufficiency Review ___________________________________________________________________________ In my capacity as the Agency Fiscal Officer of the Department of General Services (the "Department"), I hereby certify that Modification No. 1 to the infrastructure improvements for 13th Street (DCAM-21-CS-IFB-0003) with Fort Myer Construction Corporation in the amount of $6,804,102.87 is consistent with the Department’s current seller intra District capital budget and adequate funds are available in the budget for the expenditure. Per Contracts & Procurement (C&P), after Council approved the contract through CA24-0343, the Department executed Contract No. DCAM-21-CS-IFB-0003 on January 5, 2022, in the amount of $22,992,912.30. This amount included $10,000.00 for identified items (Employee Training) ineligible for capital expenditure. The item is identified in the proposal as line-Item Number 0005 of the Bid Form (Attachment J.2 of the contract). There should be no purchases, commitments, or expenditures for the identified Employee Training until operating funds are available, and a purchase order is created. The Department is now seeking approval of Modification 1 in the amount of $6,804,102.87. The Department of General Services (seller agency) has $6,804,102.87, for “capital eligible” items only, as per the District Capital Guidelines, in capital intra district funds from DMPED (buyer agency). The active seller agency project was transferred from SOAR to DIFS as a one-time action. The PASS/DIFS information is as follows: Page 2 of 2 Project Fund Imp Owner Project Name AY RQ/PO Amount Comments Number Detail AGY AGY Seller project AM0.EBK08C.ST E'S RDWYS/ created in 300028 3075750 N/A AM0 AM0 RK242915 $6,804,102.87 INFRASTR STAGE 2 SOAR transferred to DIFS TOTAL $6,804,102.87 Antoinette Hudson Beckham Agency Fiscal Officer 2000 14th St. NW, 8th Floor, Washington DC 20009 | Telephone (202) 727-2800 | Fax (202) 727-7283 GOVERNMENT OF THE DISTRICT OF COLUMBIA DEPARTMENT OF GENERAL SERVICES ___________________________________________________________________________ OFFICE OF THE GENERAL COUNSEL MEMORANDUM TO: Thomas Wells